The OBP must update the PMD of multi-market products by removing the market “GB” from the designated markets as of 1 January 2025*. As soon as the Regulation is applicable, the upload of the PMD with the market “GB” listed as one of the designated markets will not be possible. Consequently, the EU Hub will respond with an A-16 data validation error (#A16) followed by an A-22 "Market not found" (#A22) error. The request will fail and you will be required to remove the market “GB” before proceeding further with the data upload for other markets.

*The date is subject to the relevant written guarantees from the UK being in place.